Finland's data centres draw 1.2 TWh of electricity a year, which places it 28th of the 33 countries this atlas carries a figure for.
That is 1.5% of everything the country generates — above the 1.2% median across those countries.
Set against 0.3 GW of installed capacity, that implies a 49% load factor.
One metro is tracked here: Helsinki, at 190 MW and under construction.
190 MW of that is not yet operating: it is under construction or still an announcement.
Its strongest showing anywhere in the atlas is Power & Grid on the control basis, at #11 of 12.
It does not register at all on Silicon, Memory & Storage or Networking.
One supplier is domiciled here, Wärtsilä, booking roughly $7bn.
Its single strongest grip on the buildout is On-site power & backup, where firms domiciled here hold 8% of global supply in a sub-layer weighted 0.45 for how hard it is to substitute.
About $2bn of AI infrastructure investment has been announced for Finland, though announced is not built — that figure is graded C.
National context
Where Finland ranks
The same tables read three ways. A country can lead one basis and be invisible on another, and that gap is the whole point of the atlas.
| Tier | Physicalassets here | Ownershiprevenue booked | Controlcould stop you |
|---|---|---|---|
| Silicon | — | — | — |
| Memory & Storage | — | — | — |
| Networking | — | — | — |
| Systems & Facility | #28of 54 | — | — |
| Power & Grid | #29of 77 | #14of 17 | #11of 12 |
Data centre metros (1)
| Helsinki — Under constructionWaste heat recovery into district heating is standard practice. | 190 MW C |
Supply positions
Share of each global sub-layer held by firms domiciled here, and how hard that sub-layer would be to substitute. Those two multiplied are what the control basis ranks on.
Power & Grid
| Sub-layer | Share | Substitutability |
|---|---|---|
| On-site power & backup | 8% C | ×0.45 |
Strongest single grip: On-site power & backup — 8% × 0.45 substitutability weight.
Suppliers domiciled here (1)
| Wärtsilä — Balancing enginesPower & GridGrid-balancing engines increasingly contracted against DC load. | $7bn |
Revenue is the group or segment figure closest to each tier's perimeter. Segment boundaries differ between issuers, so treat the split as indicative.